Centre Pivot - Capital Cost - Break Down Price Examples
Home
Introduction
Irrigation Methods
System Selection
System Comparison
Converter
FAQ
Links
Irrigation Standards
Glossary
Bibliography
Site Map
Disclaimer
Item
Percentage of total cost
Job 1
Job 2
Center pivot/linear
34%
37%
Installation centre pivot/linear
3%
3%
Mainline/submain
4%
4%
Installation mainline/submain
2%
3%
Fittings
3%
4%
Power/control cable
2%
2%
Installation cables
1%
1%
Freight
1%
1%
Pump
14%
17%
ETRS (electric transformer)
11%
0%
Generator set
0%
16%
Electric controls
9%
11%
Telemetry (automation)
7%
0%
Weather station
3%
0%
Two soil moisture probes
5%
0%
Flowmeter
1%
1%
You are in:
Irrigation Methods
->
Sprinkler Irrigation
->
Continuous System
->
Centre Pivot
->
Capital Cost
Site maintained by
Otto
&
Babi
Szolosi
Copyright © 2004 Pratt Water Pty Ltd. All rights reserved.